Skip to main content

Stuart Street Tank Construction Project Updates

Announcement for new water storage tank construction starting in summer 2025, featuring logos from the EPA and a community service agency.
How to Stay Informed

To stay informed about the progress of this project, please visit this page regularly. We will provide ongoing updates, including construction milestones, road closures, and any potential service impacts.

Construction Progress Update
11/6/2025

Progress continues on the Stuart Street Tank Project. Over the past week, crews successfully completed horizontal seam welding on the second shell. Despite a brief half-day weather delay, all second-level joints have now been finished.

The third level of tank panels has been set and welded into place, marking another significant milestone. In the coming week, crews will begin horizontal seam welding on the third level, and the “knuckle” structural components are expected to arrive on site to support the next phase of construction.

The CCSD sincerely appreciates the community’s continued patience and understanding as this vital infrastructure project advances. Once completed, the new tanks will improve water reliability and enhance public health and safety for decades to come.

The project remains on schedule, with progress moving efficiently thanks to favorable site conditions and strong coordination among the construction team.

Construction worker welding inside a large tank structure, standing on a raised platform with ladders and equipment around.
A large metal tank with attached ladder and platform, trees and a building in the background.
Industrial construction site with large tanks, a crane lifting a tank component, ladders, equipment, and a worker guiding the process.
Construction Progress Update
11/4/2025

Construction is progressing, and the second rung is scheduled to be welded in place today.

A worker in a brown helmet and maroon hoodie welds a large cylindrical metal tank outdoors with machinery nearby.
A crane lifting a large curved metal structure, possibly part of a tank, in a construction area with trees and buildings nearby.
Construction Progress Update
10/31/2025

Work is steadily moving forward on the Stuart Street Tank Project. After mobilizing to the site last week, the tank contractor completed layout and crane setup before beginning assembly. By mid-week, crews set and welded the tank floor, and by Thursday afternoon, the full bottom radius of the tank steel was in place. Four large panels (8' × 24') were lifted and secured, with welding continuing through the end of the week.

Looking ahead; weld seams will be inspected early next week to ensure quality and compliance, followed by installation of the second row of tank panels and continued seam welding.

The CCSD sincerely thanks the community for its ongoing patience and understanding as this important project advances. Once complete, the new tank will fortify water reliability and help protect public health and safety for decades to come.

Construction Progress Update
10/23/2025

Final construction phase of the foundation for the first Stuart Street water tank is nearing completion. Backfill of the center section within the ring wall foundation was completed and inspected on Thursday, October 23rd.

The project continues with the placement of non-expansive materials to finalize the tank ring wall foundation. Tank erection is scheduled to begin Tuesday, with steel panel installation and assembly. Heavy equipment, including cranes and fabrication machinery, are now on site to support this next phase of work.

Additional project progress updates will be provided next week. The CCSD appreciates the patience and cooperation of the community during this major capital improvement project.

Construction Progress Update
9/30/2025

On September 26, 2025, the first ring wall concrete foundation was poured. We are currently allowing it to cure before proceeding with additional construction at the site.

Construction Progress Update
9/19/2025

The existing ring wall has been fully demolished and removed from the site (see photos of the giant claw excavator in action).

This past week, crews focused on over-excavation and soil compaction to prepare for upcoming concrete work. All compaction tests met or exceeded required standards.

Next week, crews will begin preparing the concrete foundation for the new ring wall.

Tank II Removal
9/2/2025

On September 2, 2025, dewatering and removal of Tank II began. As a result of this activity, you may notice water running down Ardath and Richard Streets. This is expected during the demolition process and is being managed by the construction team.

Construction Activity Update
8/22/2025

Construction activity for the Stuart Street Tank project will begin next week with the setup of the construction staging area. On September 2, 2025, dewatering and removal of Tank II will begin. 

Notice to Proceed Letter
8/5/2025
8/5/2025 Notice to Proceed Letter

 

Join our mailing list